Working document

Automation and Control System Migration Verification Checklist

A plug-and-play checklist for verifying a migrated automation or control system recipe before an engineering run: migration method documentation, independent logic review, interlock and alarm parity, historian tag mapping, and a dry-run/FAT exercising every condition, with a filled specimen.

Document typeChecklist
Topic areaTech Transfer & NPI
LevelIntermediate
UpdatedSeptember 2026
How to use this document

Copy the template below into your quality system. Replace every <<FILL: ...>> placeholder with your company, system, and process specifics, then route it through your own document control, review, and approval. The filled specimen shows one worked example; adapt the numbers and scope to your operation and verify each cited regulation or standard against the current source before you rely on it.

This is a generic, originally worded starting point. It contains no confidential, proprietary, or employer material, it is drafted with AI assistance and reviewed, it is not legal or compliance advice, and adopting it does not by itself create or prove compliance. See the Disclaimer and Terms.

This is a ready-to-use checklist for verifying that a receiving site’s automation or control system recipe is genuinely equivalent to the sending site’s before it controls an engineering run. It exists because a batch that completes successfully on a migrated recipe does not prove the recipe is correct; an interlock that silently never triggers, or an alarm threshold sitting an order of magnitude off, will not show up in a functional test of the nominal batch path. Replace every <<FILL: ...>> placeholder with your own specifics and route the completed checklist through your normal document control. A worked filled specimen follows.

Purpose

This checklist confirms, item by item, that a control system recipe or program migrated from the sending site to the receiving site for <<FILL: product / process>> has been independently verified for logical, interlock, alarm, and historian equivalence before it is relied upon for an engineering run or qualification batch.

Scope

Applies to <<FILL: recipe, program, or control system element(s)>> migrated from <<FILL: sending site platform/vendor>> to <<FILL: receiving site platform/vendor>>, whether migrated by direct export/import or manual re-creation.

Checklist

#ItemPass / Fail / NAReference / evidenceVerified byDate
1Migration method documented (direct export/import vs. manual re-creation)<<FILL>><<FILL>><<FILL>><<FILL>>
2Independent line-by-line logic review completed by someone who did not build the migrated recipe<<FILL>><<FILL>><<FILL>><<FILL>>
3Every interlock (holds, minimums, maximums, sequencing locks) verified against the sending site’s configuration, value by value<<FILL>><<FILL>><<FILL>><<FILL>>
4Every alarm setpoint and priority verified against the sending site’s configuration<<FILL>><<FILL>><<FILL>><<FILL>>
5Units of measure confirmed consistent at every migrated field (no minutes-for-hours or metric/imperial transposition)<<FILL>><<FILL>><<FILL>><<FILL>>
6Historian / data logging tag mapping verified so migrated data streams map to the correct parameters<<FILL>><<FILL>><<FILL>><<FILL>>
7Dry-run or factory acceptance test executed, deliberately exercising every interlock and alarm condition, not only the nominal batch path<<FILL>><<FILL>><<FILL>><<FILL>>
8Dry-run/FAT predicted vs. actual behavior compared and documented for every exercised condition<<FILL>><<FILL>><<FILL>><<FILL>>
9Any discrepancy found during review or dry-run dispositioned (corrected and re-verified, or documented as an intentional site-specific difference)<<FILL>><<FILL>><<FILL>><<FILL>>
10Verification record filed with the technology transfer documentation before the engineering run<<FILL>><<FILL>><<FILL>><<FILL>>

Acceptance criteria

Every item must be Pass or a documented, Quality-accepted NA before the migrated automation controls an engineering run. A Fail on any interlock, alarm, or units item holds the recipe from use until corrected and re-verified; a dry-run exercising only the nominal batch path, with interlock and alarm conditions never actually triggered and observed, does not satisfy item 7.

Filled specimen

Extract from an example transfer of Acme Therapeutics’ ATX-207 process to a CDMO running a different automation platform. Company and specifics are illustrative.

#ItemResultEvidence
1Migration method documentedPassManual re-creation documented in TTP-2026-014, section 6
2Independent logic review completedPassReviewed by automation engineer M. Osei, who did not build the recipe; review record ATN-REV-0087
3Interlocks verified value by valueFail, then Pass on re-verificationWash-step hold interlock found entered as 90 hours instead of 90 minutes; corrected and re-verified 2026-09-11
4Alarm setpoints verifiedPassAll 14 alarm setpoints matched sending-site configuration within tolerance
5Units of measure confirmed consistentFail, then PassSame units transposition as item 3, corrected at the same time
6Historian tag mapping verifiedPass22 of 22 tags mapped correctly, confirmed against sending-site historian export
7Dry-run/FAT exercising every interlock and alarmPassFAT-2026-0033 deliberately triggered all 9 interlocks and 14 alarms
8Predicted vs. actual comparedPassAll 23 conditions matched predicted behavior after the item 3/5 correction
9Discrepancies dispositionedPassUnits transposition corrected and re-verified; no other discrepancies found
10Verification record filedPassFiled with TTP-2026-014 before engineering run 1, dated 2026-09-12

The specimen shows the checklist doing its job: a real transposition error was caught at item 3 before it reached the floor, corrected, and re-verified, rather than surfacing as an unexplained process hang during the first real batch.

Common findings this checklist prevents

  • A migrated recipe verified only by a successful functional run of the normal batch sequence, with interlocks and alarms never actually triggered and observed.
  • No independent reviewer; the same person who built the migrated recipe also verified it.
  • A units transposition or similar transcription error surfacing for the first time during an engineering run, consuming a scarce batch or starting material lot.
  • Historian tag mapping assumed correct with no explicit verification, discovered wrong only when a trend report shows unexpected values.

How to adapt this checklist

  1. Expand or reduce the item list to match your own control platform’s actual configuration elements, recipes, interlocks, alarms, historian tags, sequencing logic.
  2. Name the independent reviewer requirement explicitly in your transfer plan so it is not skipped under schedule pressure.
  3. Design the dry-run or FAT script to deliberately trigger every interlock and alarm condition, not just to run the batch to completion.
  4. File the completed checklist with the technology transfer documentation before it is needed for an inspection or audit.