How to use this document
Copy the template below into your quality system. Replace every <<FILL: ...>> placeholder with your company, system, and process specifics, then route it through your own document control, review, and approval. The filled specimen shows one worked example; adapt the numbers and scope to your operation and verify each cited regulation or standard against the current source before you rely on it.
This is a generic, originally worded starting point. It contains no confidential, proprietary, or employer material, it is drafted with AI assistance and reviewed, it is not legal or compliance advice, and adopting it does not by itself create or prove compliance. See the Disclaimer and Terms.
This is a ready-to-use risk assessment for a dimension a technical and quality audit routinely misses entirely: whether the CDMO, or the parent entity that owns it, is financially stable enough to still be running your process in two or three years. A site can score well on every technical and quality dimension in the paired CDMO Technical Assessment Scorecard and still close, get sold, or get reclassified internally as a non-core asset mid-program, for reasons that have nothing to do with its equipment or its quality system. This assessment is scoped separately from capacity-reservation and slot contract terms, covered in the main article’s Technical Assessment of a CDMO Before You Sign, not here. Replace every <<FILL: ...>> placeholder with your own specifics and route it through your normal document control, review, and approval. A worked filled specimen follows. Verify each cited reference against the current source before you rely on it.
1. Purpose
This assessment evaluates the financial stability and business-continuity posture of <<FILL: CDMO name>> and, where different, its parent or ultimate owner, independently of the CDMO’s own assurances, so that a decision to rely on this site accounts for the risk that the business behind it closes, is sold, or deprioritizes the site during the life of the program.
2. Scope
3. Responsibilities
4. Methodology
Score each indicator against the evidence actually found, not the CDMO’s own assurance that “everything is fine.” Public financial disclosure exists only for a publicly traded CDMO or a publicly traded parent; for a privately held or financial-sponsor-owned site, rely on direct questions, corroborated wherever possible against trade press covering contract development and manufacturing, and treat a reluctance to answer a direct ownership or hold-period question as itself informative. This assessment does not require certainty that a site will never close or change hands; no diligence can promise that. It requires a documented answer naming the specific indicators checked and an explicit decision about whether the program’s exposure to this CDMO is proportionate to what independent verification actually found.
5. Scoring scale
6. Parent and ownership financial indicators
7. Site-specific continuity indicators
8. Regulatory continuity cross-check
A continuity risk at this CDMO is not only a schedule risk; for certain drug products it intersects a sponsor’s own notification obligation. Under FD&C Act Section 506C, an application holder must notify FDA of a permanent discontinuance, or an interruption likely to cause a meaningful supply disruption, in the manufacture of certain drug and biological products, generally at least six months in advance or, if that is not possible, as soon as practicable and no later than five business days after the interruption occurs. Section 506C(j), added by the CARES Act in March 2020, further requires certain manufacturers of drugs that are life-supporting, life-sustaining, intended to treat a debilitating disease or condition, or that would be considered critical in a public health emergency, to maintain a redundancy risk management plan evaluating supply risk at each manufacturing establishment; FDA’s draft guidance on these plans, “Risk Management Plans to Mitigate the Potential for Drug Shortages,” was published May 19, 2022, with its comment period closed July 19, 2022, and remained in draft as of this writing.
9. Residual risk acceptance and conclusion
10. References
Federal Food, Drug, and Cosmetic Act, Section 506C, notification of a permanent discontinuance or interruption in manufacturing.
Federal Food, Drug, and Cosmetic Act, Section 506C(j), redundancy risk management plans, added by the CARES Act, March 2020.
FDA draft guidance, “Risk Management Plans to Mitigate the Potential for Drug Shortages” (May 19, 2022).
21 CFR 211.180, General requirements for records retention.
ICH Q10, Pharmaceutical Quality System, management of outsourced activities.
Confirm the current version and status, draft versus final, of each reference before issue.
11. Revision history
12. Approvals
Filled specimen
Extract from an example assessment of a viral-vector CDMO for Acme Therapeutics’ ATX-520 AAV gene therapy program. Company and product are illustrative.
Conclusion: no indicator scored High, but the parent’s segment-level trend and the two-site strategic-alternatives disclosure, even though this site was not one of the two named, were judged close enough to the program’s exposure to warrant a documented mitigation rather than a clean pass. Recommendation: proceed with conditions. Acme negotiated an explicit tech-transfer-package delivery clause into the master services agreement and funded a low-volume engineering run at a smaller regional CDMO every eighteen months to keep a second source genuinely qualified, tracked in the paired CDMO Exit Readiness, Dual-Sourcing, and IP and Data Ownership Assessment.
Common inspection findings this assessment prevents
- A technical assessment reaching a recommendation based entirely on equipment and quality evidence, with no independent check of the business behind the site.
- A site-specific restructuring or “strategic alternatives” disclosure that was publicly available before signature but surfaced only after the program was already committed.
- A financial-sponsor-owned CDMO’s hold period and exit incentive never discussed, despite being a direct, answerable question.
- A continuity risk identified informally during diligence but never scored, mitigated, or risk-accepted in writing, so it quietly disappears from the program’s record.
How to adapt this assessment
- For a publicly traded CDMO or parent, pull the actual 10-K/10-Q language and the segment-level numbers directly; do not summarize from memory or from a secondary source.
- For a privately held or financial-sponsor-owned site, ask the ownership and hold-period question directly and in writing, and note explicitly if the CDMO declines to answer.
- Search trade press covering contract development and manufacturing by the specific site name, not just the parent brand, before closing the assessment.
- Score every indicator honestly against the scale in section 5, and route any High score through section 9 with a real owner, mitigation, and date.
- Revisit this assessment at each periodic reassessment of the CDMO, since a continuity risk can emerge without the CDMO proactively disclosing it.
- Confirm every reference in section 10 against the current published version, including whether the draft guidance cited has since been finalized, before issue.